Project Energy Connect Update

TransGrid have issued their update on Project Energy Connect (PEC), which showed the cost of the transmission line has almost doubled to $4.1b, which is twice that approved by the AER for the line, which was initially valued at $1.82b ($2.1b real).

With delays pushing the project’s full commissioning to late 2027—and that date still uncertain, the impact could be passed on to transmission-connected tariffs, potentially doubling them. The delays have been laid at the floor of COVID-19, labour shortages, the war in the Ukraine, floods and inflation. However, arguments are being heard that some of these should have been fully covered by contingency valuations.

In contrast the SA Electranet project has come in relatively on time and budget, again leaving questions as to why the TransGrid numbers are so much higher.

However, in good news for TransGrid, Elecnor, who in 2024 had indicated they would not be proceeding with Phase 2 of the project look to remain. They are cited as being under a fixed price arrangement of $3.6b, however they still have the option to walk away through the second stage if the project becomes unprofitable.

Overall, the re-negotiation with Elecnor will at least allow the second phase of the project to be started, a 700km line between Buronga and Wagga Wagga. However, they did not go as far as to ensure the AER additional funding would be approved or that the Elecnor issues that plagued stage 1 have been fully resolved. Overall, this is not a win for the project, the ongoing issues will lead to increased pass-through costs and likely further delays.

NEM Reform Consultation

The Department of Climate Change, Energy, Environment and Water (DCCEEW) is supporting the independent expert panel headed by Prof. Tim Nelson. The panel is preparing a roadmap and making actionable recommendations to support reforms to the NEM Wholesale Market.

The first consultation with stakeholders closed on February 14, 2025. This will be followed by a draft report in Q325, with the final report to be submitted to the Energy and Climate Change Ministerial Council in December 2025.

Investment incentives will likely focus on the several areas being looked to for comment.

The first being, can government certificated schemes promote investment in firmed, renewable generation and storage? This will favour those sites that can, via a combination of assets, likely solar, wind and battery, benefit from providing a firm, flat shape to the grid in addition to those currently in place via the CIS and LGC schemes. This will likely be welcomed by renewable developers and those retailers who have the ability to firm renewables around their existing large-scale assets. However, it will not be favoured by smaller single-site developers who will argue it will not allow competition but favour the larger participants of such a scheme. However, this could gain traction similarly to how the LGC scheme facilitated the development of 33,000,000 MWh of new renewable generation by guaranteeing a minimum certificate requirement for off-takers. Such a mechanism could potentially replace the LGC scheme post-2030, allowing for continued renewable development without requiring direct government support through programs like CIS.

The second area of focus will be the previously mentioned ESB Post-25 Capacity Mechanism scheme. Although not explicitly mentioned, it is the inference from the document’s questions. This was a controversial proposal by the ESB, as it would benefit only existing large-scale non-renewable generators at its core and could slow renewable investments. Although under a different guise, this has already occurred through the payments Origin will receive for the Eraring extension. This approach will likely continue throughout the 2020s and into the 2030s until sufficient storage and transmission infrastructure are in place to enable renewables to effectively meet the power demands of the NEM.

The wholesale market and consumer interaction will focus largely on the availability of Demand-Side Response (DSR). It may be preferable if these services can be included within the wholesale market. However, in reality, the NEM_DE (AEMO’s dispatch engine) cannot facilitate this. As such, the reforms may suggest these changes, but the likelihood of them being implemented is low.

The paper will likely result in more progressive tariffs and contracting, time-of-use reforms, and the ability to interact as an aggregated load (likely batteries) or feed-in tariffs at a time-of-use scale for consumers.

At the extreme, a full market overhaul should be proposed and will likely be presented by proponents. It is well-known that Australia operates under a pool mechanism, following previous pool models that have experienced soaring wholesale electricity prices and allowed participants to manipulate bid stacks. The likely replacement would be to move to a self-dispatch energy-only market, which would remove the requirements for capacity payments and a central dispatch model whilst encouraging competition. A reformed approach would have an underlying principle of bilateral trading where all output from generators must be contracted, removing the incentive to manipulate the prices in the pool spot market. This would bring the futures “Swap” market into a physical market, or a Futures market, which could run in parallel, as well as a “spot market”, which would run from the day ahead until just before delivery. Any imbalances not traded in these markets would be subject to imbalanced settlement pricing which could be significantly higher due to the calculations which underpin the cost of the balancing. All market participants would likely welcome this, bar those who are currently able to benefit from aggressive bidding behaviour and create a real time operating system.

This would significantly reduce AEMO’s role in the market and open up the ability for smaller generators, large off-takers and Distributed Network Operators to have access to the market and control the pricing and balance their assets in a much more controlled manner. It is likely any reforms suggesting this would receive significant lobbying and pushback within the government. PPAs and CFDs can still function within this market; however, they would be settled externally as financial products. The market, in turn, would provide better investment signals for operators and developers.

AEMC Reliability Panel Stakeholder Input

On December 12th, the AEMC released a request for stakeholder input as it commenced its System Restart panel review.

The panel are looking to review the challenges, especially around:

  • The increasing reliance on the lowered availability of System Restart Ancillary Services (SRAS) and scarcity of that capability from new transmission-connected generators.
  • The rising system restoration risks are coming about within areas of large penetration of distribution-connected PV generation.

The framework is being assessed in two stages: the first comprises a review to assess whether the current regulatory framework suits the evolving nature of the grid under the AEMO ISP, and the second revises the requirements around system restarts based on the first stage findings, considering the risks associated with major supply disruption risks and SRAR availability and costs.

In the event of a significant loss of generation and supply to consumer load, the current arrangements allow for invoking the SRAS procedures known as black start capability. This capability is usually made up of smaller, quick-to-start, smaller-generation units that can assist historically large baseload units in coming online.

Overall, the absence of this generation would primarily become problematic during a large-scale system failure, similar to the issues experienced with Callide. However, as we transition to a grid with more variable generation and fewer synchronous units, such disturbances could become more frequent. This trend may persist until sufficient storage capacity is available to stabilise the system.

Submissions close on 30/01/25, and it is likely that a significant number of differing opinions will emerge as businesses advocate for ensuring payments are available for these events. This could also strengthen the arguments being presented, following the ESB Post 25 assessment, for the introduction of a capacity mechanism for generators on the NEM.