Renewable energy storage road map released

Edge 2020 Brisbane City

The CSIRO released its Renewable Energy Storage Roadmap at the end of March 2023.

Their modelling suggested that while Australia leads the world in solar generation, and we have reduced emissions significantly, there is still a big task ahead of the country if we are to meet net zero emission targets and maintain affordable and reliable energy to end users. The CSIRO Renewable Energy Storage Roadmap report showed Australia will need significant amounts of storage to meet the transition to renewables.

Storage is the key to integrating renewable energy into the grid and reducing the dependency on coal and gas fired generation. Currently the electricity produced from renewable sources such as wind and solar is intermittent and is not easily dispatched into the grid when it is most needed. Storage allows the renewable energy to be generated when the natural resources are high and dispatching it into the grid when the electricity is needed.

Dispatchable storage is currently available in the grid in the form of pump storage hydro, such as Wivenhoe power station in Queensland and Tumut 3 in NSW. There are also various battery installations located across the NEM.

The dispatch of renewable energy may require different storage technologies to best suit an evolving NEM. Storage comes in various forms from electrochemical storage such as batteries, mechanical storage such as hydro, chemical storage and thermal storage. Each technology has its pros and cons, but a combination of technologies is likely to be required to meet the real time storage volumes and timings of the NEM.

For many years pumped hydro has been seen by governments as the solution to Australia’s energy storage needs, but timing is the limiting factor in this solution.

To enable the transition from coal and gas fired generation to renewables, storage is required now. On a typical day we have excess solar generation resulting in negative spot prices, however over the evening peak as demand increases the supply of renewable drops of coal and gas provide the generation to meet demand. Thermal generation is normally dispatched at prices higher than the cost of renewables resulting in higher spot prices. If storage could be used efficiently the solar energy produced during daylight hours could be used over the evening peak and into the evening resulting in lower electricity prices.

As coal fired generation retires between 2023 and 2035, new dispatchable generation needs to be brought online, the CSIRO report states, development timelines need to be accelerated to bring more projects online by 2030.

Pump storage hydro typically has a lead time of 10 years so either development timelines need to be accelerated or different storage technologies need to be employed in the meantime.

CSIRO chief executive said “there was a need for a “massive increase” in storage capacity to achieve the transition to net zero, with estimates of 11 to 14 gigawatts of additional storage capacity by 2030 alone.

2030 is not far away, to meet the transition targets should industry be focusing on storage rather than generation? Is storage an opportunity to utilise existing infrastructure like old mine pits for pump storage hydro or repurpose retiring thermal power station sites as storage hubs?

Solar and wind are the big losers in latest AEMO MLF forecasts

woman on a windy day

As the electricity market evolves the Australian Energy Market Operator (AEMO) makes assessments of the changing landscape from a transmission and security of supply perspective.

Recently AEMO released its final assessment of Marginal Loss Factors (MLFs). MLF determine how much energy is lost between the generator and the region reference node in each state.

In this next round of MLFs many of the big losers are the intermittent generators. Changes to the grid and the closure of thermal generators have had a detrimental impact on wind and solar farms. Lower MLF’s impact the amount of revenue generators can make.

The final MLF numbers are not as bad as what was published in AEMO draft report providing some positive news for wind and solar developers. Since the draft report new modelling has included the delayed return to service of the Callide C units.

The primary driver for changes in the new MLF forecasts has been changes in availability due to the closure of Liddell, revised return to service dates for Callide C, revised demand forecasts and the increased penetration of solar and wind generation into the grid.

Recent transmission line work has resulted in an increased capacity between Queensland and NSW which means increased flows from Queensland which results in wind and solar projects located in the north of NSW being constrained.

MLF generally gets worse for generators at the end of a long transmission lines, this has resulted in generation in northern NSW being the big loser this year. Some solar farms in the New England region have dropped by over 3%.

While a 3% fall sounds bad, it is not as bad as the MLF for Moree, a 57MW solar farm in western NSW which loses over 20% of its generation by the time it gets to the regional reference node. Previously Moree solar farm had an MLF of 0.8275, this year it is 0.7977.

The return to service of Callide C significantly impacted solar farms in central Queensland, however the delayed return to service has lessened the impact. Daydream, Collinsville, Kidston, and Moura are some of the solar farms most impacted by the new MLFs.

So what does the mean to end users? While we are seeing a rapid increase in renewable generation, the location of this generation is important to the success of a project. If we use the example of Moree where over 20% of the renewable generation does not reach the market then the question has to be, was it built in the correct part of the grid. Many people focus on the size of the project while the volume of electricity produced needs to be of greater importance. Unfavourable MLF will impact the success of the project, will reduce the renewable energy available to the market and potential can leave end users with less renewable energy than what they had signed up for.

Retrofitting old power station sites with renewable generation

wind turbine

As coal fired generation retires the logical solution would be for renwable generation developers to use the existing connection points to install either new generation or energy storage. Generally, these locations have the best transmission infrastructure close by and have favourable loss factors.

Increasingly renewable developers are finding it hard to obtain favourable locations to build new projects particularly for solar and wind. Most developers prefer sites next to transmission infrastructure, but more and more renewable developers are struggling to find sites with good solar or wind potential. The wind sector is most influenced by site selection with the majority of the high wind yielding sites already developed.

The question is, do developers now look at redeveloping existing generation sites rather than start with a greenfield site? While there are benefits of a brownfield site, the registration and connection process of a new project is as arduous as developing a whole new new site. Additional connection studies would need to be undertaken and new projects would need to meet more stringent approval processes.

As developers are forced to develop low yielding sites the output of the projects drops and costs increase, so developing an older site may be beneficial if yield is significantly better.

The earlier wind farms were built in the late 1990’s and are now entering the final years of their life. Are these locations ideal for the next generation of wind farms or will developers opt for new sites?

Overseas data suggests repowering an existing site with new more efficient and larger wind turbines has its benefits. At this stage no Australian wind farms have been repowered.

The Australian Energy Market Commission (AEMC) estimates the average wind farm is 15 years old however some are close to 30 years old. The early wind farms are located where the wind resource was seen to be the best.

With offshore wind the next big thing in the industry will we also see the development of larger more efficient wind farms on the same ground as the industry pioneers?

At Edge 2020 keeping our customers informed on the energy market is a top priority for us. As the world shifts towards a more sustainable future, we are committed to playing our part by procuring from renewable energy sources, whilst continuing to secure cost-effective energy solutions for our customers. If your business is interested in wholesale or retail renewable PPAs we’d love to help you. Contact us on: 1800 334 336 or email: info@edge2020.com.au

Coal state leading the way to renewables

Last week in Queensland the weather was perfect. It was perfect for those at the beach during school holidays but also perfect for renewable energy.

As everyone in the NEM knows, Queensland is better known for its dominant coal generation, at times pumping out 80% of Queensland’s power supply. With the clear skies and just enough wind, Queensland became the renewable state.

Last week, Queensland’s demand was supplied by over 66% renewable energy. Solar was the largest contributor of renewable energy with wind coming in second.

Previously we have seen the state powered by 50% renewables but the 66% hurdle is a positive message for end users impacted by the reliability and behaviour of the thermal generators.

The Palaszczuk government announced their 10-year-energy plan which involved introducing two new pumped hydro mega-projects in regional Queensland and a green conversion of its coal-fired power generators. The Palaszczuk government also has recently announced upping the target of 50% renewable energy by 2030 to 70% by 2032.

Despite this increase in target, until recent years coal has remained dominant in Queensland. The government has all but ruled out the early retirement of any of the state-owned coal-fired power stations, following pressure from unions. Some could say the slow uptake in renewables is due to supply chain issues, registration, connection and construction delays while other may say it results from the government owning a significant portion of the existing thermal and non-thermal generation that is reaping high returns due to the spot and forward energy prices.

AEMO’s recent Integrated System Plan (ISP) shows the NEM will contain over 80% capacity coming from renewables by 2030. While the renewable industry in Queensland has been slow to grow recently more federal funding is being used to rewire the nation by connecting renewable energy zones (REZ) to end users. With the rewiring in place developers are less restricted in building and financing renewable projects and producing renewable energy.

Industry is also looking for renewable energy to meet their sustainability targets which leads to a market for new renewable projects. AEMO indicated there are thousands of MWs of renewable projects waiting to be built.

If Queensland followed the latest ISP, the state would require an additional 30GW of energy from renewable sources and the storage required to make it useful for end users when the sun does not shine, or the wind does not blow.

Today’s announcement by the premier outlined the $62B plan for Queensland energy and jobs. The plan includes:

  • 70% of Queensland’s energy supply from renewables by 2032
  • 80% of Queensland’s energy supply from renewables by 2035
  • Two new pumped hydros at Pioneer/Burdekin and Borumba Dam by 2035
  • A new Queensland SuperGrid connecting solar, wind, battery and hydrogen generators across the State
  • Unlocking 22GW of new renewable capacity – giving Queensland 8 times the current level of renewables
  • Publicly owned coal fired-power stations to convert to clean energy hubs to transition to, for example, hydrogen power, with jobs guarantees for workers
  • Queensland’s publicly-owned coal-fired power stations to stop reliance on burning coal by 2035
  • 100,000 new jobs by 2040, most in regional Queensland
  • 11.5GW of rooftop solar and 6GW of embedded batteries
  • 95% of investment in regional Queensland
  • Building Queensland’s first hydrogen ready gas turbine

With this announcement by the Premier, Edge look forward to more renewable generation entering the market resulting in savings for end users and the planet.

If procuring renewable energy is one of your company goals, Edge2020 can help you build a PPA to support your sustainability strategies. Contact us on 1800 334 336 or info@edge2020.com.au